BCL Engineering Ltd - PROVIDING MUNICIPAL ENGINEERING SERVICES FOR OVER 40 YEARS
  • BCL
  • services
    • Water Supply & Treatment
    • Wastewater Treatment
    • Land Development
    • Transportation and Roads
    • Solid Waste
    • Buildings & Municipal Services
    • Surveys
    • Electrical Engineering
    • Storm Water & Drainage
  • Projects
  • Careers
  • Contact

PILoT BUTTE

Wastewater Treatment Upgrades

Picture

Town of Pilot Butte 
Project Value: $9,600,000
​Date Completed: 2020

Picture

PRoJECT BaCKGRoUND

The Town of Pilot Butte has grown significantly over the past 15 years, placing a burden on existing wastewater infrastructure. The Town operated a two cell facultative lagoon sized for a contributing population of approximately 2,800, which was discharged twice per year to Boggy Creek ultimately flowing to the Qu’Appelle River system through a series of surface ponds and creeks. As the discharge is to fish bearing waters, the system is required to meet federal Wastewater Systems Effluent Regulations. BCL completed a Downstream Use and Impact Study to establish new effluent targets, and followed with conceptual and preliminary design to modify the existing system process including a SAGR system.

Detailed design was completed in 2019 which includes a first treatment step of a deep aerated partial mix cell, followed by three storage cells with alum feed for phosphorus reduction, and a new pumping station which pumps the effluent into two SAGR cells for ammonia removal. The station recycles a portion of the water back to the system front end to aid in further nitrogen reduction with the remaining portion sent to effluent release. Station design includes a wet/dry style station with 5.8 m deep reinforced concrete substructure.

​Project tendering was completed using a contractor pre-qualification process in July of 2019, construction started in September 2019 and substantial completion by November 2020. The facility is the largest in its kind in Saskatchewan, with a capacity to treat wastewater from approximately 7,500 people. The upgraded facility maximized the existing lagoon infrastructure, helping reduce the overall project construction cost to an estimated $9.8M. 
Picture

PRoJECT HIGHLIGHTS

  • 100 m2 Aeration Building
  • 65 m2 Pumping Station
  • 3,200 lin.m. of 250 - 400 mm - 2.55 ha HDPE Aeration Cell
  • Two 32 m x 90 m SAGR cells - 162,500 m3 compacted clay storage cell ​​
Picture

Services Provided

  • Downstream Use Impact Study
  • Preliminary Design
  • Conceptual Layout
  • Detailed design
  • Tendering
  • Resident Engineering - Contract Admin
  • Commissioning ​​​​

PROVIDING MUNICIPAL ENGINEERING SERVICES FOR OVER 40 YEARS

Picture
Phone: 306.477.2822
​Email: [email protected]
200 - 302 Wellman Lane
Saskatoon, SK
S7T 0J1
  • BCL
  • services
    • Water Supply & Treatment
    • Wastewater Treatment
    • Land Development
    • Transportation and Roads
    • Solid Waste
    • Buildings & Municipal Services
    • Surveys
    • Electrical Engineering
    • Storm Water & Drainage
  • Projects
  • Careers
  • Contact